Approximate Timeline for the USD 211 Building Project
JH/SR High
March 2016-February 2017 New Locker Room Area and Classroom area
March 2016-August 2016 Junior High Administration and Stull Entry
May 2016-August 2016 JH Remodel and Back Stairway rebuild
Eisenhower Elementary
March 2016-October 2016 Gym/Shelter and Classroom Construction
May 2016-August 2016 Office Remodel
April 2016-July 2016 North Restrooms
November 2016-February 2017 Remodel Old Gym area to classrooms
This updated timeline would allow the project to finish in about one year and not a year and a half as originally thought. We hope the weather will cooperate and allow this to happen.