Thursday, October 15, 2015

Concept Drawings of Part of the Bond Project!

View of the front of Stull Gym when completed.

View of the front of Norton Community Jr. High when completed.
View of the interior of Eisenhower gym/shelter

Thursday, October 8, 2015

Approximate Timeline for the USD 211 Building Project 

JH/SR High

March 2016­-February 2017 New Locker Room Area and Classroom area

March 2016­-August 2016 Junior High Administration and Stull Entry

May 2016­-August 2016 JH Remodel and Back Stairway rebuild

Eisenhower Elementary

March 2016­-October 2016 Gym/Shelter and Classroom Construction

May 2016­-August 2016 Office Remodel

April 2016­-July 2016 North Restrooms

November 2016­-February 2017 Remodel Old Gym area to classrooms

This updated timeline would allow the project to finish in about one year and not a year and a half as originally thought. We hope the weather will cooperate and allow this to happen.