View of the front of Stull Gym when completed.
Thursday, October 15, 2015
Concept Drawings of Part of the Bond Project!
View of the front of Norton Community Jr. High when completed.
Thursday, October 8, 2015
Approximate Timeline for the USD 211 Building Project
JH/SR High
March 2016-February 2017 New Locker Room Area and Classroom area
March 2016-August 2016 Junior High Administration and Stull Entry
May 2016-August 2016 JH Remodel and Back Stairway rebuild
Eisenhower Elementary
March 2016-October 2016 Gym/Shelter and Classroom Construction
May 2016-August 2016 Office Remodel
April 2016-July 2016 North Restrooms
November 2016-February 2017 Remodel Old Gym area to classrooms
This updated timeline would allow the project to finish in about one year and not a year and a half as originally thought. We hope the weather will cooperate and allow this to happen.